280 High Holborn

Project Details

Client

Hines UK

Architect

GMW Architects

Contractor

Mace

Stone used

Moleanos and Thala Beige

Value

£450,000

Contract Duration

26 weeks, completed 30-09-2012

Scope of Work

External limestone cladding and internal limestone flooring

280 High Holborn, Chicester House, London WC1

280 High Holborn is a seven storey mixed use development between Holborn and Chancery Lane. Retail units are provided at the ground floor level with a self contained residential complex and 63,000 sq ft of office accommodation on the upper floors.

As part of the stonework package, awarded by main contractor Mace, Putney & Wood’s in-house design team interpreted GMW’s conceptual drawings to create detailed drawings of the stonework on each elevation. Following design, Putney & Wood’s project team sourced the specified limestones and hand fixed each one individually.

John Fraser of Mace said, “I was very pleased with Putney & Wood’s performance on this project and I’d have no problems using them on future stone jobs”.

Let's Work Together!